RV-9 Build Progress

20.7% complete · 200 hours logged · 4 sub-sections done · 2 sub-sections in progress

In Progress

Left Elevator Prime left elevator parts 75%
12 hours logged
Elevator Trim Tab Dimple elevator trim tab parts 20%
1 hour logged
Elevator Trim Tab Prime elevator trim tab parts 30%
1 hour logged

Current Issues

No current issues.

200 hours · 36 / 45 tasks
↳ Horizontal Stabilizer ✓ Done
47 hours · 5 / 5
↳ Vertical Stabilizer ✓ Done
24 hours · 7 / 7
↳ Rudder ✓ Done
46 hours · 8 / 8
↳ Right Elevator ✓ Done
38 hours · 7 / 7
↳ Left Elevator 52.8%
37 hours · 4 / 9
Prime left elevator parts 75%
↳ Elevator Trim Tab 56.3%
7 hours · 4 / 8
Dimple elevator trim tab parts 20%
Prime elevator trim tab parts 30%
0 / 17 tasks
Not started yet.
0 / 10 tasks
Not started yet.
0 / 8 tasks
Not started yet.
0 / 10 tasks
Not started yet.
0 / 9 tasks
Not started yet.
0 / 11 tasks
Not started yet.
Empennage Horizontal Stabilizer ✓ Done
47 hours · 5 tasks
Empennage Vertical Stabilizer ✓ Done
24 hours · 7 tasks
Empennage Rudder ✓ Done
46 hours · 8 tasks
Empennage Right Elevator ✓ Done
38 hours · 7 tasks
✓ 100%
1 hour
Unpack & inventory empennage kit
Empennage › Other
✓ 100%
5 hours
Deburr horizontal stabilizer parts
Empennage › Horizontal Stabilizer
✓ 100%
4 hours
Dimple horizontal stabilizer skins
Empennage › Horizontal Stabilizer
✓ 100%
7 hours
Prime horizontal stabilizer parts
Empennage › Horizontal Stabilizer
✓ 100%
13 hours
Rivet horizontal stabilizer ladder
Empennage › Horizontal Stabilizer
✓ 100%
18 hours
Rivet horizontal stabilizer skins
Empennage › Horizontal Stabilizer
✓ 100%
5 hours
Deburr vertical stabilizer parts
Empennage › Vertical Stabilizer
✓ 100%
4 hours
Dimple vertical stabilizer parts
Empennage › Vertical Stabilizer
✓ 100%
1 hour
Matchdrill FB tip fairing
Empennage › Vertical Stabilizer
✓ 100%
1 hour
Countersunk vertical stabilizer parts
Empennage › Vertical Stabilizer
✓ 100%
6 hours
Prime vertical stabilizer parts
Empennage › Vertical Stabilizer
✓ 100%
4 hours
Rivet vertical stabilizer ladder
Empennage › Vertical Stabilizer
✓ 100%
3 hours
Rivet vertical stabilizer skins
Empennage › Vertical Stabilizer
✓ 100%
2 hours
Matchdrill & Deburr rudder parts
Empennage › Rudder
✓ 100%
4 hours
Dimple rudder parts
Empennage › Rudder
✓ 100%
3 hours
Matchdrill, deburr, dimple counterweight parts
Empennage › Rudder
✓ 100%
12 hours
Prime rudder parts
Empennage › Rudder
✓ 100%
5 hours
Rivet rudder stiffeners to skins
Empennage › Rudder
✓ 100%
12 hours
Rivet rudder skeleton and skins
Empennage › Rudder
✓ 100%
4 hours
Rivet rudder trailing edge
Empennage › Rudder
✓ 100%
4 hours
Form and rivet rudder leading edge
Empennage › Rudder
✓ 100%
6 hours
Matchdrill & Deburr right elevator parts
Empennage › Right Elevator
✓ 100%
1 hour
Matchdrill, deburr counterweight parts
Empennage › Right Elevator
✓ 100%
8 hours
Dimple right elevator parts
Empennage › Right Elevator
✓ 100%
9 hours
Prime right elevator parts
Empennage › Right Elevator
✓ 100%
3 hours
Rivet right elevator stiffeners to skin
Empennage › Right Elevator
✓ 100%
9 hours
Rivet right elevator assembly
Empennage › Right Elevator
✓ 100%
3 hours
Rivet right elevator trailing edge
Empennage › Right Elevator
✓ 100%
10 hours
Matchdrill & Deburr left elevator parts
Empennage › Left Elevator
✓ 100%
5 hours
Matchdrill, deburr counterweight parts
Empennage › Left Elevator
✓ 100%
6 hours
Dimple left elevator parts
Empennage › Left Elevator
75%
12 hours
Prime left elevator parts
Empennage › Left Elevator
✓ 100%
4 hours
Matchdrill & Deburr trim servo parts
Empennage › Left Elevator
0%
—
Rivet left elevator stiffeners to skin
Empennage › Left Elevator
0%
—
Rivet left elevator assembly
Empennage › Left Elevator
0%
—
Rivet left elevator trailing edge
Empennage › Left Elevator
0%
—
Rivet trim servo parts
Empennage › Left Elevator
✓ 100%
1 hour
Deburr elevator trim tab parts
Empennage › Elevator Trim Tab
✓ 100%
1 hour
Fabricate/Adjust trim tab Horn
Empennage › Elevator Trim Tab
✓ 100%
1 hour
Fabricate (3D print) trim tab Ribs
Empennage › Elevator Trim Tab
✓ 100%
1 hour
Cut and Match Drill trim tab Hinge
Empennage › Elevator Trim Tab
20%
1 hour
Dimple elevator trim tab parts
Empennage › Elevator Trim Tab
0%
1 hour
Bend elevator trim tab and fit assembly
Empennage › Elevator Trim Tab
30%
1 hour
Prime elevator trim tab parts
Empennage › Elevator Trim Tab
0%
—
Assemble elevator trim tab parts
Empennage › Elevator Trim Tab
0%
—
Unpack & inventory wing kit
Wings › Other
0%
—
Deburr & prime wing spar components
Wings › Wing Spars
0%
—
Assemble main wing spar
Wings › Wing Spars
0%
—
Deburr wing ribs
Wings › Ribs
0%
—
Prime wing ribs
Wings › Ribs
0%
—
Assemble wing skeleton (spars + ribs)
Wings › Ribs
0%
—
Deburr & dimple wing skins
Wings › Wing Skins
0%
—
Rivet top wing skins
Wings › Wing Skins
0%
—
Rivet bottom wing skins
Wings › Wing Skins
0%
—
Build left fuel tank
Wings › Fuel Tanks
0%
—
Build right fuel tank
Wings › Fuel Tanks
0%
—
Pressure test fuel tanks
Wings › Fuel Tanks
0%
—
Build left aileron
Wings › Ailerons
0%
—
Build right aileron
Wings › Ailerons
0%
—
Build left flap
Wings › Flaps
0%
—
Build right flap
Wings › Flaps
0%
—
Install wingtips
Wings › Wingtip
0%
—
Unpack & inventory fuselage kit
Fuselage › Other
0%
—
Deburr & prep fuselage bulkhead parts
Fuselage › Bulkheads
0%
—
Assemble aft fuselage bulkheads
Fuselage › Bulkheads
0%
—
Rivet aft fuselage skins
Fuselage › Aft Fuselage
0%
—
Assemble forward fuselage bottom skin
Fuselage › Forward Fuselage
0%
—
Assemble forward fuselage sides
Fuselage › Forward Fuselage
0%
—
Install seat floors and ribs
Fuselage › Seat / Floor
0%
—
Build & attach canopy frame
Fuselage › Canopy
0%
—
Fit & trim canopy plexi
Fuselage › Canopy
0%
—
Bond canopy to frame
Fuselage › Canopy
0%
—
Install main landing gear legs
Finishing Kit › Landing Gear
0%
—
Install nose gear / tailwheel
Finishing Kit › Landing Gear
0%
—
Install brakes & wheels
Finishing Kit › Landing Gear
0%
—
Install control sticks & pushrods
Finishing Kit › Control System
0%
—
Install rudder pedals
Finishing Kit › Control System
0%
—
Install flap actuator & motor
Finishing Kit › Control System
0%
—
Fit & trim cowling
Finishing Kit › Cowling
0%
—
Install cowling hinges & fasteners
Finishing Kit › Cowling
0%
—
Fabricate & fit wheel pants
Finishing Kit › Fairings
0%
—
Fabricate & fit wing root fairings
Finishing Kit › Fairings
0%
—
Prep & prime firewall
Engine › Firewall
0%
—
Install firewall penetrations & fittings
Engine › Firewall
0%
—
Install engine mount
Engine › Engine Mount
0%
—
Hang engine
Engine › Engine Mount
0%
—
Connect engine controls & linkages
Engine › Engine Mount
0%
—
Install exhaust system
Engine › Exhaust
0%
—
Install fuel lines & selector valve
Engine › Fuel System
0%
—
Install engine baffles & cooling system
Engine › Cooling System
0%
—
Design avionics panel layout
Avionics › Panel
0%
—
Fabricate & mount instrument panel
Avionics › Panel
0%
—
Run and terminate main wiring harness
Avionics › Wiring
0%
—
Install circuit breakers & bus
Avionics › Wiring
0%
—
Install EFIS / displays
Avionics › Instruments
0%
—
Install pitot-static system
Avionics › Instruments
0%
—
Install transponder & encoder
Avionics › Comm / Nav
0%
—
Install comm radio & intercom
Avionics › Comm / Nav
0%
—
Install nav, strobe & landing lights
Avionics › Lighting
0%
—
Mate wings to fuselage
Final Assembly › Rigging
0%
—
Attach empennage to fuselage
Final Assembly › Rigging
0%
—
Rig ailerons & flaps
Final Assembly › Rigging
0%
—
Rig elevator & rudder
Final Assembly › Rigging
0%
—
Install & rig elevator trim
Final Assembly › Rigging
0%
—
Fuel system ground test
Final Assembly › Ground Tests
0%
—
Electrical system ground test
Final Assembly › Ground Tests
0%
—
Engine ground run
Final Assembly › Ground Tests
0%
—
Flight control full & free check
Final Assembly › Ground Tests
0%
—
Obtain airworthiness certificate
Final Assembly › Certification
0%
—
Phase 1 flight test program
Final Assembly › Flight Tests

Last synced: 2026-10-27 04:20:02 GMT-0800 - Data from Notion Build Tracker