RV-9 Build Progress

5.2%
Overall Progress
18
Hours Logged
2
Tasks Complete
of 90 total
5
In Progress

Progress by Section

Section Progress Status Hours Tasks
Empennage
18.6% 18.0 2 / 25

Currently In Progress

Deburr horizontal stabilizer parts
Horizontal Stabilizer
90%
Dimple horizontal stabilizer skins
Horizontal Stabilizer
50%
Prime horizontal stabilizer parts
Horizontal Stabilizer
90%
Rivet horizontal stabilizer ladder
Horizontal Stabilizer
30%
Rivet horizontal stabilizer skins
Horizontal Stabilizer
5%

Open Issues

Horizontal Stabilizer Rivet horizontal stabilizer skins
Issue
Dent got created on the left skin.
Status
We decided to replace the left skin. Part is on order
Horizontal Stabilizer Rivet horizontal stabilizer ladder
Issue
One hole at the aft spar doubler got countersunk the wrong side.
Status
Resolved. Vans is ok with doing a double flush rivet for this hole.